After several months of excavation and off haul, the One Rincon Hill Phase 2 project is finally at the bottom of excavation. As excavation completes, Webcor builders were able to pour the remainder of the concrete slab to complete the underpinning. In the middle of the project site, an elevator pit was dug out and received a concrete under-slab.Waterproofing was placed in this pit on Wednesday, while rebar and concrete quickly filled it in. The project is ready for rebar installation which, upon completion, will prepare Webcor for foundation concrete pour. The expected date to place foundation is November 17th. During construction activity, the Harrison Street off ramp will be closed. The closure begins at 10:00 pm on November 16th and will continue through 10:00 pm on November 17th. N...